A coating project is an inconvenience however it is done, and the longer it runs the more it gets in the way of the work the building is there to do. The price you agree is never the whole cost. The rest shows up as delay, and delay almost always comes down to who you hired.
Most of the causes are the same four: the crew does not arrive when they said, the material is not on the shelf, there are not enough people on site to hold the schedule, or the equipment is being rented a day at a time. None of those are your fault, and all of them are yours to pay for. So the money is well spent at the front end, choosing carefully.
Start with the manufacturer, not a search
Ask the coating manufacturer who applies their product in your area, and ask for at least three projects you can call. A manufacturer knows which applicators follow the application instructions, which ones have been trained on the product, and which ones have been doing it long enough to have met most problems already. A search engine knows none of that.
On a ceiling this matters more than on most trades, because the product and the method are the same thing. A coating applied too heavily bridges the perforations in acoustical tile and takes the sound absorption with it, and the ceiling looks better on the day while performing worse for the next fifteen years. A reference from a friend will not surface that.
Recommendations from people you know are worth having but they are second tier. All you learn is that on one job, of one kind, the work went well. A contractor can be excellent on walls and partitions and know very little about an acoustical ceiling, where the tile has to stay in the grid and keep absorbing sound afterward.
Price on its own tells you nothing
The bid that comes in well under the others is usually not carrying the same materials or the same labor. If it were, the numbers would be close. Whatever has been taken out stays taken out long after the contractor has gone, and you pay for it then instead.
Six things to ask every bidder
Which products, and why. Listen for a reason that is about performance: it holds its color, it is easier to maintain, it lasts. Be wary of “it is just as good as anything else and it is cheaper”. Ask whether the manufacturer has test data behind the recommendation. A professional knows that data exists and will hand it over.
A certificate of insurance, made out to you. Not a photocopy of a general certificate. The contractor asks their agent to issue one with your name and address as the holder, and you can ask to be listed as an additional insured rather than just a holder. Accidents happen to good contractors. The question is who pays.
A start date and a finish date. Plenty of contractors will commit to starting and go quiet about finishing. Both dates should be agreed, both should be conservative, and there is nothing wrong with a penalty for missing the second one.
A payment schedule weighted to the end. Some money up front is normal, because materials have to be bought and crews blocked out. Too much up front is a signal, usually that they have no credit with their supplier or that they are paying off the last job with your money. A contractor confident in their own work will accept a third on completion. One who is not will push for ninety percent early.
Who is on site. Permanent crews the contractor has trained, or people picked up for the week. Both exist. They do not produce the same work.
Whose equipment. On a commercial job that needs lifts or scaffold, owning the equipment usually means the business is built to last rather than assembled per project.
Score it rather than feel it
A proposal that carries only a price is an invitation to trouble. Put the bidders side by side and grade each one out of ten on products and documentation, insurance, schedule, payment terms, people and equipment, and price. Add it up. Check the highest scorer with the Better Business Bureau before you sign.
No scoring system is perfect. Any system beats none.