Four hundred thousand square feet, in place


What happened
The deadline
Labor Day. The building had one summer to be ready in and a fixed date on the other side of it, set by people coming back into the building rather than by the construction schedule.
The constraint
Four hundred thousand square feet, in one summer, with other trades already working elsewhere in the building.
How it ran
Two crews worked two shifts a day through the summer, zoned floor by floor so that other trades were not disturbed. The coating was applied in place, with no demolition and no material deliveries beyond the coating itself.
The result
Complete on schedule, before the deadline. The result led on to ceiling work in Amtrak stations in other states.
Four hundred thousand square feet, in one summer.
Pace, against a date that could not move
Four hundred thousand square feet in five weeks answers the question of whether restoration can run at the pace of a large building on a date that cannot move.
It also shows the pattern that tends to follow a first project with a transportation client. The headquarters comes first, and the stations follow.