Case study

Staples

Twenty-two thousand square feet in three nights, in a one-week window the contractor did not choose.

Client

Staples, through Conner Construction

Locations

New York City area

Square footage

22,000 sq ft

Timeline

Three nights

22,000Square feet of sales floorNew York City area
3Nights to complete, against a one-week windowRetail build-out
4Days of labor cost handed back to the contractorProject record
30%Saved against replacement, passed to the retailerApproximate
The project

What happened

The window

Conner Construction had a one-week window to turn over a 22,000 square foot location, and the ceiling was inside it. The window was chosen by the retailer’s schedule rather than by the contractor.

Everything else in the build-out had to happen in the same week.

What we did

The ceiling was coated in three nights, in place, around a build-out that was still running during the day.

The result

Four days of labor cost went back to the contractor, and a saving of about thirty percent against replacement went to the retailer.

The wider point

General contractors are not the end client, but they decide what gets specified when a schedule is tight, and they keep the days that get handed back.

The contractor kept the four days.

Why it matters

The argument that reaches the next bid

Finishing in three nights against a one-week allowance is what gets a restoration line into a general contractor’s next bid.

A saving the retailer can see and four days the contractor can reuse are two different arguments for the same decision, which is why this project keeps coming up.

Outcome

Finished in three nights against a one-week window. Four days of labor cost handed back to the contractor and a thirty percent saving passed to the retailer.