What happened
The window
Conner Construction had a one-week window to turn over a 22,000 square foot location, and the ceiling was inside it. The window was chosen by the retailer’s schedule rather than by the contractor.
Everything else in the build-out had to happen in the same week.
What we did
The ceiling was coated in three nights, in place, around a build-out that was still running during the day.
The result
Four days of labor cost went back to the contractor, and a saving of about thirty percent against replacement went to the retailer.
The wider point
General contractors are not the end client, but they decide what gets specified when a schedule is tight, and they keep the days that get handed back.
The contractor kept the four days.
The argument that reaches the next bid
Finishing in three nights against a one-week allowance is what gets a restoration line into a general contractor’s next bid.
A saving the retailer can see and four days the contractor can reuse are two different arguments for the same decision, which is why this project keeps coming up.