What happened
The problem
A national department store chain needed its ceilings brought back across a large part of its portfolio, without closing a single store and without a capital replacement budget.
Replacement would have meant a dumpster at the back door of forty-one stores, tile stacked in aisles, and sections of sales floor roped off for as long as it took.
The scale
Forty-one locations across twenty-nine states, including Alaska. 4,305,000 square feet of acoustical tile, suspension grid and air diffusers.
How it ran
Twenty-seven crews on a rolling schedule of one to two stores a week over seven months. Each store was worked after close and open for business the next morning.
The result
No tile removed, no material stored on site, and no location lost a day of business. About fifty percent saved against the conventional route.
On a program this size, that difference is the reason the work happened at all.
The restoration figure fit a maintenance budget. The replacement figure did not.
The program that proves the network
Twenty-seven crews working to one specification across twenty-nine states is a different proposition from one good crew in one state, and it is the question every national construction director asks first.
A single excellent project does not tell you whether a supplier can hold a standard at pace across a whole retail chain. Forty-one of them does.